Riveted UniPanel and Built-in Pedestal Set
|
UniPanel is made of riveted galvanized steel, which contributes strength without welding. This enables the system features as 100 percent recyclable. The pedestal sets are fixed at hexagon-shape openings at four corners of the panel body. On top of the pedestal, there is a 4 mm hexagon punched hole, which provides height adjustment from top by using of 4 mm hex key wrench.
|
|
|
|
Installation
|
1.
|
Assembly of UniPanel in job site: For 76 mm and 100 mm height installation, Pedestal-Sets are recommended to ship to and fix to panel body at the job site. For 60 mm height installation, pedestals may be fixed either at factory or at the job site depending on the job site plan.
|
2.
|
Decide the starting line, Connection of Base Connector to UniPanel is easy. Reticulated Cable Trenches formed automatically.
|
|
3.
|
Height 60 mm and 76 mm installation: Follow the floor contour, to maintain steady Cable Trench clearance for cable routing.
|
4.
|
Install steel caps on Cable Trenches.
|
5.
|
Height adjustment at deviation point
|
|
Step 1:1
|
loose lock-nut from below by 17 mm wrench
|
|
|
|
Step 2:1
|
Adjust height from top by 4 mm hex key wrench
|
|
Step 3:1
|
Fasten lock-nut from below by 17 mm wrench
|
|
|
6.
|
Leveling installation: for height 100 mm ~ 120 mm
|
|
|
|
Step 1:
|
Laser alignment to locate deviation.
|
Step 2:
|
square aluminum tub (4 meter plus) for measurement.
|
Step 3:
|
Adjust by 4 mm hexagon key wrench.
|
Step 4:
|
Fasten the lock-nut at below by 17 mm wrench.
|